Set the rate of customer demand to get takt time. Each process step's ideal cycle time is stretched by its availability, performance and quality losses to give a net cycle time. Any step whose net cycle time is longer than takt cannot keep pace with demand. Steps far below takt have spare capacity, which shows up as overproduction risk if they are run flat out.
Edit any data box. Values are percentages except ideal cycle time (seconds).
| Step | OEE | Net cycle time (s) | % of takt | Capacity / day | Gap to demand / day | Status |
|---|
How the numbers work. Takt time = available production time ÷ customer demand. Net cycle time = ideal cycle time ÷ (availability × performance × quality), which is the ideal cycle time divided by the step's OEE. Daily capacity = available time ÷ net cycle time.
About the example data. Availability values and the labeler before/after figures follow the Evocon draft article. The draft gives actual cycle times, not ideal cycle times; the ideal cycle times, performance and quality percentages here are illustrative values chosen so that actual cycle time = ideal ÷ performance matches the draft. They are not measured data.
Simplification. Losses are treated as independent per step, buffers are assumed large enough to decouple steps, and starved or blocked time is not modelled.